Gate One: Request for Proposal

From GICLWiki
Jump to: navigation, search

Introduction

The primary objective of gate one was to start the group thinking on the project. Disassembling and analyzing the scooter in one go without concocting a plan first would likely end in failure. A plan was created during this phase of the project that dictated how the work would proceed. Reasonable deadlines were set to keep the group in check and on time. This was also a good time to assess the group's collective strengths and weaknesses and decide how to work around any problems we would likely encounter.

Shortcomings

  • Group members not familiar with updating Wiki
  • No previous Solid Modeling experience
  • No previous knowledge of the workings of electric scooters



Initial Product Assessment

Task Deadlines

1. Request for Proposal : 10/09
1.1. Complete Work Proposal : 10/07
1.2. Complete Management Proposal 10/03
1.3. Progress Review 10/08
1.4. Familiarization with Wiki 10/08
2. Preliminary Design Review 10/30
2.1. Disassemble product and label components 10/07-10/24
2.2. Progress Review 10/24
2.3. Add all information to the Wiki 10/09-10/30
3. Coordination Review 11/30
3.1. Create Component list summary 10/10-11/14
3.2. Complete an Engineering analysis of each component 10/10-10/14
3.3. Learn and complete Solid Model 10/30-11/21
3.4. Review Progress 11/21-11/30
3.5. Post information to the Wiki 10/30-11/30
4. Reassembly 12/7
4.1. Reassemble the product 11/30-12/05
4.2. Answer the given questions about reassembly 12/04-12/06
4.3. Post information to the Wiki 12/05-12/07
5. Delivery 12/01-12/08

Ganttchart.jpg

Group 30 - Electric Scooter