This is Group 4's final presentation of our dissasembly project. Our group was assigned a Lawn Mower Engine, and this project consisted of five required deliverable gates, as listed at the bottom of this page. The 5th gate consisted of a final Wikipedia page such as this. Our group members are listed below, and with this are the jobs and tasks that each person was assigned to do. Our Management and Project Plans are listed on this page for easy access, and this information can also be found via the link in Gate 1. Throughout the navigation of this site, information can be found as to what tools were used, how difficult each component was to dissasemble, recommended design revisions, as well as other various pieces of information. We hope that you find this information well suitable to your needs.


Management Plan

Our group plans to meet on a regular basis with specific objectives in mind each meeting. We plan to meet Mondays and Wednesdays, after class lecture at 5:00PM, in the project lab (Furnas 621). If needed, we will also meet on Thursdays in this same location at 3:30PM to finish what was not completed at the previous meetings. We can be contacted about our progress through the group manager’s email, sblyons@buffalo.edu. The group positions are as follows: Sean Lyons is the Project Manager, Jessie Allen is the Communication Liaison, Bhushan Karayilthekkoot is the Solid Modeling Expert, and Tom Schuler is the Wiki Expert. A table of our intended work timeline and position responsibilities outline are given below:

Along with these individual group tasks, each member is expected to contribute to the project write-ups as a whole to distribute work fairly and evenly.



Meeting Date..............Goals

10/12--------------------------Product Dissection

10/14--------------------------Product Dissection

10/19--------------------------Product Dissection

10/21--------------------------Product Dissection

10/26--------------------------Product Dissection

10/28--------------------------Product Dissection Write-up

11/2----------------------------Component Summary

11/4----------------------------Design Revisions

11/9----------------------------Solid Modeled Assembly

11/11--------------------------Engineering Analysis

11/16--------------------------Coordination Review

11/18--------------------------Coordination Review

11/23--------------------------Coordination Review

11/25--------------------------Coordination Review

11/30--------------------------Product Reassembly

12/2----------------------------Product Reassembly

12/7----------------------------Final Report

12/9----------------------------Final Report

Group Members

Sean Lyons - Project Manager: - Set goals for each meeting and see that they are accomplished. - Divide work among each member each meeting. - Manage meeting work time

Jessie Allen - Communication Liaison: - Email members meeting times and goals. - Organize group work into reports.

Bhushan Karayilthekkoot - Solid Modeling Expert: - Perform solid modeling tasks.

Tom Schuler - Wiki Expert: - Publish group work to the internet on our wiki page and manage it.

Bob Belko - Disassembling/Assembling Expert: - In charge of Disassembling/Assembling the lawn mower engine.

Lawn Mower Engine

ADSC00160.jpg ADSC00161.jpg
(A) (B)

Fig 1: (A) The top of the lawn mower engine; & (B) the same engine at a different view

Gate 1

The link below leads to group 4's gate 1.

Gate 1 for group 4

Gate 2

The link below leads to group 4's gate 2.

Gate 2 for Group 4

Gate 3

The link below leads to group 4's gate 3.

Gate 3 for Group 4

Gate 4

The link below leads to group 4's gate 4.

Gate 4 for Group 4