==Project Timeline==
 +
====''' Table 1: Weekly Schedule '''====
 +
 +
{| class="wikitable"
 +
|-
 +
! scope="col"|
 +
! scope="col"| Week of Sept 10
 +
! scope="col"| Week of Sept 17
 +
! scope="col"| Week of Sept 24
 +
! scope="col"| Week of Oct 1
 +
! scope="col"| Week of Oct 8
 +
! scope="col"| Week of Oct 15
 +
! scope="col"| Week of Oct 22
 +
! scope="col"| Week of Oct 29
 +
! scope="col"| Week of Nov 5
 +
! scope="col"| Week of Nov 12
 +
! scope="col"| Week of Nov 19
 +
! scope="col"| Week of Nov 26
 +
! scope="col"| Week of Dec 3
 +
! scope="col"| Week of Dec 10
 +
|-
 +
!scope="row"| Monday Meeting
 +
|style="background-color: #fe0000;" |
 +
|style="background-color: #fe0000;" |
 +
|style="background-color: #fe0000;" |
 +
|style="background-color: #fe0000;" |
 +
|style="background-color: #fe0000;" |
 +
|style="background-color: #fe0000;" |
 +
|style="background-color: #fe0000;" |
 +
|style="background-color: #ffffcc;" |
 +
|style="background-color: #ffffcc;" |
 +
|style="background-color: #ffffcc;" |
 +
|style="background-color: #ffffcc;" |
 +
|style="background-color: #ffffcc;" |
 +
|style="background-color: #ffffcc;" |
 +
|style="background-color: #ffffcc;" |
 +
|-
 +
! scope="row"| Product Proposal:
 +
|style="background-color: #fe0000;" |
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|-
 +
! scope="row"| Section 1: The Four Factors
 +
|style="background-color: #fe0000;" |
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|-
 +
! scope="row"| Section 2: Product Complexity
 +
|style="background-color: #fe0000;" |
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|-
 +
! scope="row"| Section 3: Product Cost and Ownership
 +
|style="background-color: #fe0000;" |
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|-
 +
! scope="row"| Turn in Product Proposal
 +
|style="background-color: #fe0000;" |Due 9/12
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|-
 +
! scope="row"| Gate 1:
 +
|
 +
|
 +
|
 +
|style="background-color: #fe0000;" |
 +
|style="background-color: #fe0000;" |
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|-
 +
! scope="row"| Work Proposal
 +
|
 +
|
 +
|
 +
|style="background-color: #fe0000;" |
 +
|style="background-color: #fe0000;" |
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|-
 +
! scope="row"| Management Proposal
 +
|
 +
|
 +
|
 +
|style="background-color: #fe0000;" |
 +
|style="background-color: #fe0000;" |
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|-
 +
! scope="row"| Product Archaeology
 +
|
 +
|
 +
|
 +
|style="background-color: #fe0000;" |
 +
|style="background-color: #fe0000;" |
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|-
 +
! scope="row"| Wiki Update
 +
|
 +
|
 +
|
 +
|style="background-color: #fe0000;" |
 +
|style="background-color: #fe0000;" |
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|-
 +
! scope="row"|Turn in Gate 1
 +
|
 +
|
 +
|
 +
|
 +
|style="background-color: #fe0000;" |Due 10/8
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|-
 +
! scope="row"| Gate 2:
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|style="background-color: #fe0000;" |
 +
|style="background-color: #fe0000;" |
 +
|-
 +
! scope="row"| Preliminary Project Review
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|style="background-color: #fe0000;" |
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|-
 +
! scope="row"|Dissection
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|style="background-color: #fe0000;" |
 +
|style="background-color: #fe0000;" |
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|-
 +
! scope="row"| Wiki Update
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|style="background-color: #fe0000;" |
 +
|style="background-color: #fe0000;" |
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|-
 +
! scope="row"| Turn in Gate 2
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|style="background-color: #fe0000;" |Due 10/26
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|-
 +
! scope="row"| Gate 3:
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|style="background-color: #df7401;" |
 +
|style="background-color: #df7401;" |
 +
|style="background-color: #df7401;" |
 +
|-
 +
! scope="row"| Cause for Corrective Action
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|style="background-color: #df7401;" |
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|-
 +
! scope="row"| Component Summary
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|style="background-color: #df7401;" |
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|-
 +
! scope="row"| Product Analysis
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|style="background-color: #df7401;" |
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|-
 +
! scope="row"| Solid Modeled Assembly
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|style="background-color: #df7401;" |
 +
|style="background-color: #df7401;" |
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|-
 +
! scope="row"| Engineering Analysis
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|style="background-color: #df7401;" |
 +
|
 +
|
 +
|
 +
|
 +
|-
 +
! scope="row"| Design Revisions
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|style="background-color: #df7401;" |
 +
|
 +
|
 +
|
 +
|
 +
|-
 +
! scope="row"| Wiki Update
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|style="background-color: #df7401;" |
 +
|style="background-color: #df7401;" |
 +
|style="background-color: #df7401;" |
 +
|
 +
|
 +
|
 +
|
 +
|-
 +
! scope="row"| Turn in Gate 3
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|style="background-color: #df7401;" |Due 11/16
 +
|
 +
|
 +
|
 +
|
 +
|-
 +
! scope="row"| Gate 4:
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|style="background-color: #40ff00;" |
 +
|style="background-color: #40ff00;" |
 +
|
 +
|
 +
|-
 +
! scope="row"| Cause for Corrective Action
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|style="background-color: #40ff00;" |
 +
|
 +
|
 +
|
 +
|-
 +
! scope="row"| Product Reassembly
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|style="background-color: #40ff00;" |
 +
|
 +
|
 +
|
 +
|-
 +
! scope="row"| Mechanisms
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|style="background-color: #40ff00;" |
 +
|
 +
|
 +
|-
 +
! scope="row"| Design Revisions
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|style="background-color: #40ff00;" |
 +
|
 +
|
 +
|-
 +
! scope="row"| Wiki Update
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|style="background-color: #40ff00;" |
 +
|style="background-color: #40ff00;" |
 +
|
 +
|
 +
|-
 +
! scope="row"| Turn in Gate 4
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|style="background-color: #40ff00;" |Due 11/30
 +
|
 +
|
 +
|-
 +
! scope="row"| Gate 5:
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|style="background-color: #642efe;" |
 +
|style="background-color: #642efe;" |
 +
|-
 +
! scope="row"| Finalization of Deliverables
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|style="background-color: #642efe;" |
 +
|
 +
|-
 +
! scope="row"| Final Assessment
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|style="background-color: #642efe;" |
 +
|
 +
|-
 +
! scope="row"| Technical Report
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|style="background-color: #642efe;" |
 +
|style="background-color: #642efe;" |
 +
|-
 +
! scope="row"| Oral Presentation
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|style="background-color: #642efe;" |Date TBD
 +
|-
 +
! scope="row"| Wiki Update
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|style="background-color: #642efe;" |
 +
|style="background-color: #642efe;" |
 +
|-
 +
! scope="row"| Turn in Gate 5
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|style="background-color: #642efe;" |Due 12/ 14
 +
|-
 +
|}
 +
 +
{| class="wikitable"
 +
!colspan="2"|Key
 +
|-
 +
|rowspan="1"|Monday Meeting
 +
|style="background-color: #ffffcc;"|
 +
|-
 +
|rowspan="1"|Proposal
 +
|style="background-color: #fafa47;"|
 +
|-
 +
|rowspan="1"|Gate 1 Tasks
 +
|style="background-color: #4a8bf2;"|
 +
|-
 +
|rowspan="1"|Gate 2 Tasks
 +
|style="background-color: #df013a;"|
 +
|-
 +
|rowspan="1"|Gate 3 Tasks
 +
|style="background-color: #df7401;"|
 +
|-
 +
|rowspan="1"|Gate 4 Tasks
 +
|style="background-color: #40ff00;"|
 +
|-
 +
|rowspan="1"|Gate 5 Tasks
 +
|style="background-color: #642efe;"|
 +
|-
 +
|rowspan="1"|Finished Tasks
 +
|style="background-color: #fe0000;"|
 
|}
 
|}

Revision as of 17:16, 13 December 2012

This is a reference page for Group 21. The timeline contains each gate and what is to be finished. Specific tasks were assigned to each group member and due dates were given.


Project Team

Nicholas Harrison Mechanisms Expert His responsibilities include finishing the mechanisms part of the gate as well as making one design revision. email- nlharris@buffalo.edu
Jonathan Hughes Dissection Expert His responsibilities include reassembling the product, product reassembly write up, as well as making one design revision. email- jhughes5@buffalo.edu
Garrett Rice Presenter His responsibilities will include creating the slide show for the design revision and presenting to the class during on the assigned day. email- gmrice@buffalo.edu
Tiffany Vinette Wiki Expert Her responsibilities include programming the wiki, allowing for appropriate technical communication. All finished parts of the gates are to be sent to her email before Thursday at 5pm. She is also responsible for the project management portion of the project and completing one design revision. email- tvinette@buffalo.edu
Elizabeth Moon Photographer Her responsibilities include overseeing the assembly, noting any problems that may have occurred, while taking photographs. She will also be responsible for one design revision. email- esmoon@buffalo.edu

Project Timeline

Table 1: Weekly Schedule

Week of Sept 10 Week of Sept 17 Week of Sept 24 Week of Oct 1 Week of Oct 8 Week of Oct 15 Week of Oct 22 Week of Oct 29 Week of Nov 5 Week of Nov 12 Week of Nov 19 Week of Nov 26 Week of Dec 3 Week of Dec 10
Monday Meeting
Product Proposal:
Section 1: The Four Factors
Section 2: Product Complexity
Section 3: Product Cost and Ownership
Turn in Product Proposal Due 9/12
Gate 1:
Work Proposal
Management Proposal
Product Archaeology
Wiki Update
Turn in Gate 1 Due 10/8
Gate 2:
Preliminary Project Review
Dissection
Wiki Update
Turn in Gate 2 Due 10/26
Gate 3:
Cause for Corrective Action
Component Summary
Product Analysis
Solid Modeled Assembly
Engineering Analysis
Design Revisions
Wiki Update
Turn in Gate 3 Due 11/16
Gate 4:
Cause for Corrective Action
Product Reassembly
Mechanisms
Design Revisions
Wiki Update
Turn in Gate 4 Due 11/30
Gate 5:
Finalization of Deliverables
Final Assessment
Technical Report
Oral Presentation Date TBD
Wiki Update
Turn in Gate 5 Due 12/ 14
Key
Monday Meeting
Proposal
Gate 1 Tasks
Gate 2 Tasks
Gate 3 Tasks
Gate 4 Tasks
Gate 5 Tasks
Finished Tasks